Central Park Land Release (Stage 13A) | Construction Update 27th September 2016

IMG_0013.JPG

Construction Update:

  • Half way through drainage of lots.
  • Storm water to the rear of lots moving along well, almost complete.
  • Lime stabliser has started at 4pm on the 27th of September, 2016.
  • Layer of rock going down morning of the 28th of September, 2016. 
  • This layer of rock allows equipment to move around more freely on the site, so that we can beat the rain that’s coming.
  • Hazelwood Drive will be opened up next week for construction. 
  • Internal roads (all roads except Hazelwood) have been boxed out.
  • Next week we will start boxing the road on Hazelwood Drive.